Contract Factory

21 September 2026

A practical sequence of actions for a Russian company: order preparation, selection and verification of the manufacturer, technical approval, contract, payments, production control, delivery, and acceptance.

The instruction is designed for a commercial supply from China to Russia. Specific requirements for the particular product shall be clarified separately.

1. Formulate the order and allocate the tasks

Start with a description of the result: what product or equipment is needed, for what purpose, in what quantity, where it will be used, and by what date it must be received. Determine whether you are buying a standard model, ordering a modification, or commissioning development based on your own drawings. This determines the scope of the technical specification, the need for a sample, testing, and production tooling. For the first inquiry, use the standard technical specification template and fill in at least the key parameters.

Set a ceiling budget not only for the purchase, but also for obtaining a product fit for use. Clarify the required date at your own warehouse or the date of the equipment's readiness for operation. Do not substitute it with the date of completion of production. Provide the factory with information on the operating conditions of the product: loads, temperature, humidity, power supply, contact with other materials or equipment. Do not expect the manufacturer to guess the Russian conditions on its own.

Appoint a single person responsible for the order. Determine who approves technical decisions, agrees the contract, authorizes payments, reviews the inspection report, and accepts the goods. One employee may combine roles, but the authority must be clear. Inform the factory who is entitled to change the requirements and confirm the launch. Create a single order folder and keep in it the documents, correspondence, versions of drawings, and adopted decisions. Identify the Russian importer and the roles of the Chinese participants in advance.

The seller, the manufacturer, the exporter, and the payment recipient may be different companies. This is not in itself a reason to reject the deal automatically, but the links between them must be ascertained and documented. Do not start negotiations on a substantial advance payment until it is clear who is liable to you for the goods and to whom the money will be transferred. Before material expenditure, provide the product description to the customs representative and the conformity specialist. Ask them to determine the preliminary classification, applicable requirements, the set of documents, the need for testing, marking, and permits. The mandatory conformity assessment procedures are determined by the applicable technical regulation; a single foreign certificate or the seller's promise is not sufficient to conclude that the Russian requirements have been met.

At the same time, ascertain the possibility of export from China and the feasibility of payments. For potentially controlled products, request verification of the characteristics, the end user, the purpose, and the current restrictions. In case of doubt, engage a specialized expert.

The outcome of the first stage is a clear description of the order, the allocation of tasks, and a preliminary confirmation of the feasibility of the transaction. If a prohibition or the absence of the necessary permitting route is identified, resolve that issue first, rather than paying for the manufacture.

2. Find factories and obtain comparable quotations

Look for manufacturers through industry trade shows, professional associations, online marketplaces, referrals, and specialized agents. Use these channels as a way to gather candidates, not as proof of their reliability. A polished website, a platform badge, and a manager's confident communication are no substitute for verifying the legal entity and the production facility. At the first stage, it is more important to obtain several substantive replies to an identical request than a long list of names. Send the candidates one description of the product, the same planned batch, and a single list of questions.

Request them to specify the price and currency, the scope of supply, the minimum order quantity, the validity period of the quotation, the production lead time, the payment terms, and the delivery basis. Separately inquire about the cost of a sample, development work, molds, or other tooling.

Clarify whether packaging, documentation, testing, and any required modifications are included in the price or will be charged separately.

Find out which operations the factory performs itself and which it outsources to other enterprises. Request the address of the specific site where your order is planned to be produced.

Ask them to show comparable products and to explain on what equipment the critical operations are performed. For a complex product, clarify the availability of materials and components, quality control, and the production workload.

Instead of a general question such as "can you make it?", ask about specific parameters and the method of verifying the result. If a trading company is responding, do not demand that it pretend to be a factory. Establish its actual role: production management, export, financing, or support services. Determine whether you will have access to the manufacturer and to inspection, who will sign the contract, and who will remedy the defects. If the intermediary conceals the identity of the manufacturer where production control is required, this is a material obstacle that must be resolved before selecting the supplier.

Bring the quotations to the same basis. Prices without packaging and export cannot be compared directly with a price that includes delivery to the warehouse. Likewise, goods made of different materials, with different scopes of supply, and with different warranties cannot be treated as identical.

Ask the candidates to disclose in writing the exceptions to your request. If the price is noticeably lower than the others, check whether important components, tests, or operations have been excluded; do not explain the difference merely by the benefit of a "direct order."

Based on the correspondence, select a candidate for in-depth verification and, if necessary, a backup one. Do not promise an order in exchange for a discount before verification and approval of the requirements. Keep the quotations together with their dates and clarifications. The outcome of the stage is not a final choice based on the lowest price, but a clear proposal from a specific company: what it will manufacture, at which site, for what amount, within what period, and subject to what limitations. For the next step, open the supplier verification checklist from the toolbox.

3. Verify the company and its production capabilities

Request a valid business license, the full Chinese name, the Unified Social Credit Code, the registered address, and the production address. Clarify the legal representative and the authority of the employee who is handling the transaction. Match records by the Chinese name and the registration code, not merely by the English brand. If the contract, the correspondence, and the payment details relate to different entities, obtain an explanation and supporting documents.

Check the available registration information, the company's status, material changes, administrative violations, and signs of problematic activities. Use government sources and additional commercial services as provided by the annex on access to databases. If necessary, examine court and enforcement records, credit materials, and the financial statements that the supplier is entitled to provide. Assess any discovered dispute by the company's role, the subject matter, the amount, and the outcome, not merely by the fact of a mention.

It is not required to register the Russian company in all verification systems. Distinguish between public search, an employee's personal account, corporate access, and obtaining a report on the supplier's authorization. If a resource is unavailable, record the limitation and use a permissible alternative: company documents, another source, or a separate verification service. Do not circumvent platform rules. The absence of a search result means only that no result was found, not that the counterparty's reliability has been proven.

Verify that the intended site exists and is capable of fulfilling your order. For a new, technically complex, or financially substantial project, arrange a production audit or an on-site inspection. If you use video communication, request a substantive examination of the address, the production lines, the materials, the ongoing operations, and the quality control; record the limitations of such an inspection. A presentation of equipment without confirmation of the site and of actual operation is not equivalent to an audit.

Request examples of comparable orders, information on available capacity, and references that can be verified without breaching confidentiality. Clarify the origin of critical components and the dependence on subcontractors. Check the parties and the goods against applicable sanctions and export restrictions, as well as the restrictions of the servicing organizations. For controlled products of the PRC, requirements regarding the end user and the end use apply; do not limit yourself to checking the general name of the goods.

Document the decision on the supplier: what has been confirmed, what remains unknown, and by what conditions you are reducing the risk. These may include a smaller first batch, a sample, additional inspection, or a different payment scheme. Do not proceed with the transaction if the party to the contract has not been established, the substitution of the payment recipient is unexplained, or the necessary control has been refused. Where competencies are lacking, send the Center for Comprehensive Support of Foreign Economic Activity (ЦКРКДС) a specific assignment: information on the company, the goods, the stage of the transaction, and the questions to be verified. Do not treat mere contact with a partner as a completed verification.

4. Approve the technical specification

Use the technical specification template from the toolbox as the primary document describing what the factory must manufacture. Record the product name and purpose, models and article numbers, quantity, materials, dimensions, tolerances, functional characteristics, and the scope of supply. For a complex product, specify the composition of assemblies and the critical components. If an equivalent is permitted, define the criteria for its selection and the approval procedure. Do not allow substitution by the vague phrase "equivalent quality."

Link every material requirement to a method of verification. For dimensions, a tolerance and a measuring instrument are needed; for load-bearing capacity, the test conditions and duration; for output, the input materials, the operating mode, and the method of recording the result. Separate mandatory characteristics from desirable improvements. Do not write "compliance with all standards" without defining the applicable requirements. The inspector and the factory must have an identical understanding of what constitutes conformity and non-conformity.

Describe separately the adaptation to Russian use. For equipment, this covers power supply, connections, climate, consumables, software, safety, installation, and maintenance. For a consumer product, the requirements for materials, the language of the information, consumer packaging, and traceability, where applicable. Agree the required documents, tests, and marking with a conformity specialist before manufacture. Do not postpone the preparation of mandatory labeling until the goods arrive without an agreed lawful procedure.

Record the packaging and transport protection: the dimensions and weight of packages, the arrangement of contents, securing, protection against moisture and corrosion, and the requirements for loading and handling. Specify package marking, the link between the package number and its contents, and the need for serial or batch identification. Provide for the set of documentation: the instruction manual, the product passport, diagrams, the list of spare parts, and other necessary materials. Define the language and format explicitly rather than implying them by the word "documents."

Provide the factory with drawings and annexes bearing version numbers. Obtain a written response on disputed requirements: what is accepted, what requires a change in price or technology, and what the manufacturer is unable to fulfill. Check the terminology and units in the Russian and Chinese versions. If machine translation is used, an competent specialist must verify the important technical parameters and limitations. Resolve any discrepancy in translation before signing, not after production has begun.

Sign the approved technical specification and define its place among the contractual documents. Specify what takes precedence in the event of a conflict between the text, the drawing, the sample, and the specification. List any remaining open questions explicitly and set a deadline for their resolution. Do not launch the series if critical materials, parameters, or acceptance tests have not been defined.

The outcome of the stage is a single agreed technical basis on which the goods can be manufactured, the inspection can be carried out, and a claim can be substantiated.

5. Approve the sample and the change control rules

Decide what confirmation is required before the series: a standard sample, a refined prototype, a pre-series item, or a pilot batch. For simple finished products, verification of an existing model may be sufficient; for a new design, tests under an agreed program are needed. Order the sample against a specific version of the technical specification. Define in advance its cost, lead time, delivery method, verification procedure, and the consequences of an unsatisfactory result.

Do not limit yourself to assessing the appearance. Check the functions, dimensions, materials, scope of supply, compatibility, packaging, and critical operating conditions. If a property cannot be confirmed visually, use measurement or testing. For equipment, agree on the factory acceptance test and what will additionally be checked after installation in Russia. Record the results: what has been checked, by what method, what deviations have been found, and which questions remain open.

After a successful verification, approve the reference sample and link it to the version of the technical specification. Keep the identifier, photographs, the protocol, and, if necessary, a control copy at your premises or at the contractor's. Clarify which properties the sample confirms and which are assessed only from the drawings or through tests. The sample itself must not override the written requirements for safety and hidden characteristics. If the manufacturer changes the technology for the series, request confirmation that the required properties are preserved.

Establish a simple change procedure. The factory or the buyer submits a description of the change, the reason, and its impact on price, lead time, quality, tests, and documents. Authorized persons decide in writing. After that, the technical specification, drawings, specification, and, if necessary, the contract are updated. Until the change is approved, the previously agreed version remains in force. A manager's phrase "it will be better this way" is not permission to substitute a material or component.

If you are paying for development work, molds, dies, or fixtures, separately agree on the rights to the results, the ownership of the tooling, its marking, storage, maintenance, access, and transfer upon termination of the cooperation. Define the right to use the drawings, software, and trademark. Before transferring sensitive files, agree on confidentiality and the permitted circle of recipients. For a substantial project, ask a lawyer to check how these provisions will work in practice.

For the first order, consider a small verification batch instead of immediate scaling. Its purpose is to confirm the repeatability of quality, the operation of the document flow, payments, and delivery. Determine the size on the basis of economics and risk, not by a universal rule of thumb.

The outcome of the stage is an approved sample or otherwise acceptable confirmation, closed remarks, and a clear change control procedure. Send the confirmation for launching the series separately, indicating the current version.

6. Calculate the budget and agree on the delivery terms

Calculate the cost of obtaining the required result, not only the factory price. Include manufacturing, development and samples, tooling, inspections, tests, documents, packaging, inland transportation within China, export clearance, international delivery, and insurance. Add terminal operations, storage, customs payments, agent services, banking costs, and delivery to your warehouse. For equipment, take into account unloading, installation, commissioning, training, and the first spare parts.

Distinguish the economic cost from the need for cash. For example, import VAT must be taken into account when planning payments; the possibility and conditions of its subsequent deduction are to be clarified with an accountant in relation to your company. Include a reasonable reserve for changes in exchange rates, deadlines, and additional work, without presenting it as a mandatory norm. Check whether funds are sufficient for all stages up to acceptance, not only for the advance payment and the payment to the factory.

Before signing the contract, obtain a proposal from a carrier or freight forwarder based on the actual characteristics of the cargo. Provide the addresses, the number of packages, the weight, the dimensions, the value, the readiness dates, and the handling features. For dangerous, temperature-sensitive, heavy, or oversized cargo, report its special properties immediately. Compare sea, rail, road, and combined routes by the cost to the required destination, reliability, and transshipment risks, not only by the declared transit time.

Agree on the delivery rule, the exact place, and the edition of Incoterms. Ask a specialist to explain separately: who books the carriage, who pays for each leg, who handles export and import clearance, and at what point the risk passes. Incoterms do not govern the transfer of ownership, the payment schedule, or the claims procedure — these matters must be fixed in the contract.

Do not treat the seller's payment of the delivery as a promise to bear the risk until arrival. Under the Group C terms, the place of destination and the point of risk transfer differ; therefore, check the chosen basis and the availability of the required insurance. For insurance, provide the route and the properties of the cargo, and clarify the period of coverage, the risks, the exclusions, the deductible, the insured amount, and the notification procedure. Replace the promise that "everything is insured" with specific agreed terms and a document.

Obtain a written proposal listing the included and excluded costs, the conditions for storage and demurrage, the validity period of the rate, and the procedure for changing the route. Find out who is actually responsible for the different legs of the carriage and to whom a claim should be addressed. Do not confirm an "all-inclusive" option if the importer and the documents for lawful import are unclear.

The outcome of the stage is a realistic budget, the selected logistics scheme, and a distribution of responsibilities with no unaccounted-for legs of the journey.

7. Sign the contract with the annexes

Take the bilingual template from the toolbox and adapt it to the specific parties and the order. State the seller's full Chinese name, registration code, address, and the authority of the signatory. Check whether the signature or the seal belongs to the intended legal entity; the seal itself does not replace verification of the signatory's authority. If the manufacturer, the exporter, or the payment recipient differ from the seller, formalize their role and its effect on the obligations. The buyer must understand against whom to assert claims.

Fix in the contract and the specification the goods, the quantity, the price, the currency, the composition of costs, the delivery terms, and the specific deadlines. Distinguish the completion of manufacture, the inspection, the handover to the carrier, the arrival, and the final acceptance. Indicate from which event the production period starts: for example, from the fulfillment of the agreed preconditions. Do not leave the factory an opportunity to postpone the start of the term indefinitely by referring to unapproved data that has in fact already been provided.

Attach the technical specification, the drawings, the sample approval, the schedule, and the quality control procedure. Establish the inspector's access, the list of checks, the submission of the report, the correction of defects, and a re-inspection. Determine who pays for additional inspections caused by confirmed defects. Directly agree the conditions for release of the shipment and their link to the milestone payments. The inspector's report by itself does not create the right to withhold any payment if the contract provides for a different procedure.

Describe the acceptance after arrival, the verification of hidden defects, the warranty period, and the moment of its commencement. Agree on the notification of defects, the evidence, and the remedies: repair, replacement, completion of the supply, a price reduction, or a refund in the provided cases. For equipment, fix the installation, the testing, the training, and the handover of the documentation. Distinguish the acceptance of quantity, of quality, of the commissioning works, and the completion of the warranty obligations.

Establish liability for delay and breach of quality, the procedure for notifying about obstacles, and the actions in case of impossibility of payment or of obtaining a permit. Define the conditions for termination and the refund of the unearned advance. Separately fix the ownership of the goods and the tooling. Agree on the applicable law, the precise mechanism of dispute resolution, the place and language of the proceedings, the procedure for sending notifications, and the priority of the language version. Do not leave the general phrase "the dispute is resolved in arbitration" without specification.

Before signing, reconcile the Russian and Chinese versions, all the annexes, and the numbering. Check that the contract does not contradict the payment and transport scheme. For a substantial, new, or technically complex transaction, submit the draft to a specialized lawyer. Do not sign a template with blank material terms or references to missing annexes. The outcome of the stage is a signed set of documents from which the parties' obligations, the criteria of performance, and the actions upon breach are clear.

8. Arrange the payments and the currency control

Discuss the payment scheme with the bank before you commit to transferring the advance within a short period. Provide the draft contract, the description of the goods, the participants, the currency, the amount, and the beneficiary's details. Ask the bank to check the feasibility of servicing the transaction, the set of documents, the commissions, the restrictions, and the expected actions in case of a return or a delay of the transfer. Clarify with the seller whether his bank is ready to accept such a payment. Keep the answers, but do not treat a preliminary consultation as a guarantee of future crediting.

Choose the amount of the advance and the subsequent stages taking into account the risk, the nature of production, and your negotiating position. Where possible, link the payments to verifiable events: the approval of the sample, the confirmation of the materials, the readiness of the batch, the inspection, the handover of the required documents. Do not apply a universal percentage scheme to every order. Assess with particular care a full prepayment to a new supplier when the goods have not yet been manufactured and you have no independent confirmation of production readiness.

If you are considering a letter of credit, first make sure that the participating banks can service it and that the terms are acceptable to both parties. Agree on the list of documents, their issuers, the dates, the deadlines for presentation, and the permissible discrepancies. If independent quality control matters to you, discuss the inclusion of an appropriate inspection document. A letter of credit ties the payment to documentary conditions; it does not replace the verification of the physical goods and the fulfillment of the technical specification.

A payment to a third party or through a company in a foreign jurisdiction requires a separate review. Establish the legal basis, the actual recipient, the connection with the seller, the cost of the service, and the confirmation of the discharge of your obligation. Agree the documents with the bank and a lawyer before transferring. Do not conceal the participants, the goods, or the purpose; do not split payments to circumvent control. The existence of a working channel used by another buyer does not confirm the admissibility of your transaction.

Before each transfer, reconcile the contract, the invoice, the beneficiary, and the amount. Confirm any change of banking details not by replying to a suspicious e-mail, but through a previously verified contact and with the proper documents. Do not transfer a commercial payment to a manager's personal card. If there is an unexpected demand to urgently change the bank or the country of the recipient, suspend the transfer and re-check the chain. Agree on who bears the commissions and what amount must actually be received by the seller.

With the bank, determine the need for contract registration, the list of confirmations, and the deadlines for their submission. In Russia, contracts are registered with unique numbers instead of the former transaction passport; the current conditions must be clarified for your own transaction, without relying on outdated thresholds from past correspondence. (Bank of Russia) Keep the payment confirmations and verify that the seller has actually received the money. In case of a refund, find out the reason before making a repeated transfer; if the deadlines, the recipient, or the contract change, agree on and formalize the amendments.

The outcome of the stage is a lawful documented settlement scheme and a clear calendar of banking obligations.

9. Monitor production and quality

Start production with a written message after the conditions stipulated in the contract have been fulfilled. State the order number, the version of the technical specification, the agreed drawings, the sample, and the schedule. Obtain the factory's confirmation. If a separate trial stage is provided for, do not allow the series to start automatically upon its completion: first assess the results and formalize the decision. For production with a long cycle, agree in advance on intermediate status reports and access for verifying critical operations.

Monitor the actual stages: the ordering of materials, their arrival, the start of processing, assembly, testing, and packaging. Request substantive reports with dates and the identification of your order. Photographs of similar products without a link to the batch do not confirm its readiness. If the factory reports a delay, find out the reason, the affected operations, and the new plan. Before consenting to a postponement, check the consequences for transportation, your obligations to customers, and the payment schedule.

Select the types of control according to the risk. A pre-production check is needed to confirm the initial readiness; an in-process inspection serves to detect errors before the entire batch is completed; a pre-shipment inspection assesses the finished goods and the packaging. Container loading control serves a different purpose: it helps to match the inspected batch with the cargo actually being handed over. Do not treat any single inspection as a universal substitute for all the others. Use the inspection procedures and report form from the toolbox, adapting them to your product.

Before the visit, provide the inspector with the current technical specification, the drawings, the sample or its description, the list of tests, the quantity of goods, and the acceptance criteria. Agree on access to the packaging, the measuring instruments, and the relevant operations. If sampling is used, define its plan and acceptance criteria in advance; do not automatically insert generic values for different products. For critical properties, provide suitable tests or a 100% check, where this is justified and agreed.

Obtain a report identifying the site and the batch, the scope of the examination, the measurements, the test results, the defects, and the photographs. Unverified parameters and limitations must be visible separately: inaccessible samples, no power supply, incomplete packaging, or an unprepared test bench. "Not checked" does not mean "conforming." Assess the sufficiency of the verification before deciding on the payment and the shipment. The inspection report does not replace the mandatory conformity assessment and the subsequent acceptance.

In case of defects, agree on the list of corrections, the deadlines, the responsibility for the costs, and a re-check. Do not accept the promise "we will fix it before shipment" without confirmation of the result. If a deviation is acceptable to you, formalize your consent with a specific scope and the consequences for the price or the warranty. After a positive decision, record the identifiers of the batch, the packaging, and, where applicable, the seals.

The outcome of the stage is a clear decision on the verified goods, not just the received report file.

10. Prepare and reconcile the documents

Determine the set of documents before shipment together with the seller, the carrier, the bank, and the customs representative. Use the five standard forms from the toolbox, but do not require all documents automatically for every shipment. The composition depends on the goods, the route, the terms of settlement and import. Appoint those responsible for preparation, verification, and handover. Agree on the deadlines, the language, the electronic versions, and the originals, if needed. Do not wait for the cargo's arrival to discover that a mandatory document is missing.

The commercial invoice is prepared for a specific shipment. Check the number, the date, the parties, the description of the goods, the quantity, the units, the prices, the currency, the total, and the delivery terms. Clarify which transport and other costs are included in the amount. The details must correspond to the agreed payment scheme. Do not replace the final commercial document with a preliminary offer without checking its purpose and suitability. Reconcile the amounts and the description with the contract and with the batch actually being shipped.

The packing list must show the contents of the physical packages, their numbers, markings, weights, and dimensions. For mixed packaging, disclose the composition of the goods, but do not count the weight of one package again for each goods line. Distinguish the number of items, boxes, pallets, and containers. Reconcile the totals for the goods with the invoice and link the packaging to the actual marking. After loading, clarify the containers and the seals, if applicable.

For the certificate of origin, first determine the necessity and the appropriate type of document. The country of dispatch by itself does not prove the origin, and the existence of a certificate does not automatically imply a tariff preference. Instruct the exporter to arrange it through the proper channel; for example, the CCPIT system provides for a separate category of non-preferential certificates. (CCPIT) Check the link with the invoice, the goods, the quantity, and the production data. The template from the toolbox is a preparation tool, not an issued certificate; official marks must not be filled in on your own.

For sea carriage, agree on the draft bill of lading: the shipper, the consignee, the notify party, the route, the number of packages, the description, the weights, the containers, the seals, and the terms of freight payment. Separately determine the type of transport document and the procedure for the release of the goods; the carriers' requirements differ depending on the documentary scheme. For rail, road, or air carriage, use the corresponding waybill. A bill of lading is not required merely because it is included in the toolbox.

For the customs declaration, provide verified source documents to the declarant or the customs representative. Check the draft description, the code, the quantity, the weight, the origin, the value, and the permits; the established form of the declaration is governed by Decision No. 257. (EAEU) The end-to-end reconciliation must explain the differences, not create a formal match of incorrect data. Reconcile the approved draft again with the final issued documents.

The outcome of the stage is a согласованный set of documents relating to a single shipment and a clear procedure for obtaining any missing confirmations.

11. Ship the goods and arrange the import

Before handing the goods over to the carrier, make sure that the contractual conditions of shipment have been fulfilled, that the critical remarks of the inspection have been closed out, and that the required permits have been prepared. For products subject to export control, make sure that the license or other prescribed document has been obtained and corresponds to the specific transaction. Chinese rules provide for end-user and end-use control, so changes to these data must not be treated as an ordinary amendment to the transport instruction.

Check the readiness of the packaging and the transport. Agree on the time of presentation, the address, the person responsible for loading, the equipment, the securing, and the unloading at the destination. For a container, provide for a check of its condition, the matching of the numbers, and the fixing of the seal. Where necessary, arrange supervision of the loading. Keep the photographs, the information on the packages, and the handover documents. Clarify from which event the insurance operates and what is required to confirm the start of coverage.

Hand over the agreed instructions to the carrier in good time. They must contain the correct parties, the description, the number of packages, the weights, and the transport data; under the carrier's conditions, the shipper himself is responsible for the correctness of the submitted information. Check the draft and the final document. If an intermediary or several levels of transport documents are used, find out who releases the goods to the consignee and what confirmations are needed for that. Do not allow a situation where the cargo has arrived while the release procedure has not been agreed.

Track not only the expected date of arrival, but also the actual receipt of the cargo, the departure, the transshipments, and the changes of route. Agree on the procedure for notifications of delays. If the route changes, check the cost, the insurance, the permits, and the documents, especially for controlled goods. Before arrival, confirm the readiness of the customs representative, the warehouse, the funds for clearance, and the onward carriage. Clarify the free storage periods and the consequences of their expiry, without relying on a verbal promise.

Provide the declarant with the documents needed to substantiate the classification, the value, the origin, and compliance with the restrictions. The customs value does not always coincide with the invoice total; ask to see the grounds and the calculation as applied to your shipment. Answer the requests through the agreed channel, keeping the information you have provided. Do not try to reduce the payments by an inaccurate value, code, or description. If an error is discovered, discuss the lawful procedure for its correction before taking further steps.

Obtain the confirmation of release and arrange the delivery to the warehouse. Distinguish between customs release, the release of the goods by the carrier, and your acceptance of quality — these are different actions. Certificates of conformity and the marking must also be arranged at the proper moment under the applicable requirements, and not be replaced by the mere fact of crossing the border.

The outcome of the stage is a lawfully imported batch handed over with clear documents, ready for incoming inspection.

12. Accept the goods and close the order

Prepare the acceptance in advance: the responsible employee, access to the specification and the packing list, the place of examination, unloading, and the necessary instruments. Upon receipt, inspect the transport and the packaging before losing the possibility to record their condition. Check the seals, the number of packages, the marking, visible damage, and traces of opening or wetting. In case of discrepancies, make precise reservations in the transport documents, draw up an act and a photo record; do not sign without remarks if any are found.

After unloading, carry out the incoming acceptance in accordance with the technical specification and the contract. Reconcile the quantity, the completeness, the models, the serial numbers, the documentation, and the agreed parameters. For equipment, perform the stipulated installation, testing, and verification with the working materials. The factory test does not replace all the actions after installation, if the contract provides for a separate acceptance. Record what has been accepted, what has been partially checked, and which obligations of the manufacturer remain unfulfilled.

If a defect is detected, stop unsafe use and preserve the evidence. Do not discard the packaging, the seals, or the damaged parts until agreed with the interested parties, unless this creates a hazard. Record the batch number, the item, the conditions of examination, the measurements, and the signs of damage. Where necessary, engage an independent specialist. If urgent action is needed to mitigate the damage, document it and notify the relevant participants in good time.

Determine the possible addressee of claims: the factory, the carrier, the freight forwarder, or the insurer. The cause and the liability may not be clear at once, so do not postpone the mandatory notifications until the dispute with one party is completed. Take the deadlines from the contract, the conditions of carriage, the policy, and the applicable rules. Send the claim to the agreed addresses with a description of the breach, the evidence, the required remedy, and the deadline for a response. Confirm any verbal arrangement on repair or compensation in writing.

Carry out the final settlements only in the manner established by the contract, and confirm the fulfillment of the banking obligations. Hand over to the accounting department the payment and import documents, the acts, and the information on additional costs. Reconcile the mutual settlements with the seller and the contractors. Keep in one folder the signed contract, the current technical specification, the decisions on amendments, the sample or its identifier, the inspections, the shipping documents, the declaration, the acceptance, and the warranty correspondence. The end of the delivery does not mean the end of the warranty.

Before reordering, assess the quality, the deadlines, the actual costs, the operation of the settlements, and the handling of remarks. Confirm the currency of the details, the requirements, and the production site; do not automatically carry over the old terms to a new batch.

If you need help, send a substantive request to the CKRKDS stating the goods, the details of the factory, the documents, the stage of the transaction, and the desired outcome. The scope of the service, the performer, the deadlines, the price, and the liability are to be agreed separately. The methodological toolkit helps to organize the work, but it does not replace a specific assignment to a lawyer, an inspector, a bank, or a carrier.

Other solutions
Quick start in China
Step-by-step guide: How to register a legal entity in China
Quick start in China
The Right Way to Start your Business in Russia
A packaged solution for Chinese entrepreneurs
The Right Way to Start your Business in Russia
Join us in WeChat
Join us in WeChat
Our WeChat ID - rucn28
Присоединяйтесь к нам в WeChat
Присоединяйтесь к нам в WeChat
Наш ID в WeChat — rucn28